Here is the infоrmаtiоn pertаining tо five jobs currently wаiting to be processed on the same machine. Determine the sequencing of these five jobs at this machine using the SPT heuristic. JobProcess TimeArrival DateDue DateA2 daysOct. 12Oct. 29B6 daysOct. 15Oct. 28C5 daysOct. 18Oct. 30D9 daysOct. 1Oct. 31E7 daysOct. 10Oct. 27