University A is undertаking а prоject described with the fоllоwing informаtion. Answer the following four questions. ACTIVITY IMMIDEIATE PREDICESSOR COMPLETION TIME (WEEKS) A -- 3 B A 6 C A 10 D A 11 E B 8 F C,D 5 G E,F 6 The indirect costs are $400 if the project duration is 25 weeks. You can save $40 for every week you save from crashing the project. Without considering the cost, what is the shortest possible completion time? ACTIVITY NORMAL TIME NORMAL COST $ CRASH TIME CRASH COST $ A 3 50 2 70 B 6 80 4 160 C 10 60 9 90 D 11 50 7 150 E 8 100 6 160 F 5 40 4 70 G 6 70 6 70 (Study Guide Question)