Refer tо the fоllоwing diаgrаm for the project of building а house. (a) What is the earliest start time of job 2? [BLANK-1] (b) What is the latest finish time of job 4? [BLANK-2] (c) What is the slack time of job 6? [BLANK-3] (d) What is the latest start time of job 7? [BLANK-4] (e) What is the earliest finish time of job 8? [BLANK-5] (f) List the critical activities. The critical path is 1 - [BLANK-6] - [BLANK-7] - [BLANK-8] - [BLANK-9] - 9 (g) Determine the expected duration of the project. The expected project duration is [BLANK-10].