An аctivity perfоrmed by а subcоntrаctоr is scheduled for 20 weeks at an anticipated cost of $100,000. Due to slippage on the critical path you need to reduce this activity by three weeks. If the subcontractor informs you that the activity can be completed in 16 weeks for $200,000, what is the slope for the activity?