Use the fоllоwing tаble tо аnswer the questions. Cаlculate expected days for each task (round nearest whole). Task Description Pred. Optimistic Days Likely Days Pessimistic Days A Design snowman - 1 2 5 B Coordinate volunteers - 5 7 15 C Collect decorations A, B 8 10 20 D Make snow B 9 11 20 E Build snowman D 14 16 30 F Decorate C, E 2 4 8 G Ceremony F 1 1 1 Questions Project duration = [a] days Slack for task C = [b] days Early finish of task F is [c] days It makes sense for tasks D and E to be laddered. How many days would the combined duration for these 2 tasks be REDUCED by if each could be divided into 3 equal subtasks? [d] Calculate task variances (nearest 2 decimals) to determine the project standard deviation. Project standard deviation (nearest 2 decimals) = [e] If you want to be 80% confident the project will be completed on time, how many days (nearest whole) must be ADDED to the duration? [f] days If you want to be 97% confident the project will be completed on time, how many days (nearest whole) must be ADDED to the duration? [g]