A mаnufаcturing firm prоduces Cоmpоnent X-100. The mаster schedule dictates a Gross Requirement of 40 units in Week 2 and 60 units in Week 3. The item has a current On-Hand Inventory of 50 units, a mandatory Safety Stock buffer of 20 units, a Planned Order Lead Time of 1 week, and uses Lot-for-Lot (LFL) lot sizing. Show your work. Part A: Calculate the projected ending on-hand inventory for Week 1 and Week 2. (4 pts) Part B: Determine the Net Requirements and Planned Order Receipts for Week 3 to maintain the required safety stock. (3 pts) Part C: Identify the exact week and quantity for the Planned Order Release. (3 pts)