A manufacturer planned to use $94 of materials per unit prod…
A manufacturer planned to use $94 of materials per unit produced, but in the most recent period it actually used $92 of material per unit produced. During this same period, the company planned to produce 2,520 units, but actually produced only 2,200 units. The flexible-budget variance for materials is: