Three (3) eggs are boiled and all weigh 2g. The eggs are pla…
Three (3) eggs are boiled and all weigh 2g. The eggs are placed in a 15% solution of NaCl and reweighed after 30 minutes.The results:Egg 1 weighed 2.5 gramsEgg 2 weighed 2.0 gramsEgg 3 weighed 1.8 grams The solution in the container is hypertonic to which egg?
Read DetailsYou are examining the inside of a cell and notice a structur…
You are examining the inside of a cell and notice a structure that has some unique qualities. You determine that the structure is found in the cytoplasm, and some are also associated with a membrane. A colleague was able to identify that the structure is composed of two pieces that are composed of RNA and proteins. Which structure have you identified?
Read DetailsOwner (“O”) hires BuildCo (“B”) as general contractor to con…
Owner (“O”) hires BuildCo (“B”) as general contractor to construct a medical office building for a lump sum of $10 million. The contract includes: A “no oral modifications” clause, requiring written, signed change orders for any adjustments to price or schedule. A provision that only O’s “Authorized Representative,” named in the contract as the Director of Facilities, may approve change orders. A clause that progress payments are acceptance of work “to date,” but not a waiver of claims that have been properly reserved in writing.” During construction, O’s on-site project manager (“PM”), who is not the named Authorized Representative, discovers a significant design issue: the specified foundation is inadequate given subsurface conditions. PM emails B: “Proceed immediately with the deeper caissons and upgraded rebar; we’ll sort out the price in a change order later. We must keep the schedule.” B replies: “Understood. We’ll proceed with the revised foundation. We will seek an equitable adjustment to contract price and time, which we expressly reserve.” B performs the additional work. The cost of the extra foundation work, supported by detailed cost records, is $800,000 above what the original foundation would have cost. O’s accounting department, unaware of the unresolved change, later approves and pays several progress payment applications that itemize “Foundation Work – Extra Deep Caissons” in B’s schedule of values, but no formal, signed change order is ever issued. At project closeout, O refuses to pay the $800,000 extra, arguing: There is no written change order signed by the Authorized Representative, as required by the contract, and PM lacked authority to modify the contract. In a jurisdiction that follows mainstream U.S. common-law contract principles, which of the following is the most accurate statement about B’s likelihood of recovering the $800,000?
Read Details