Q8) Pleаse shоw yоur wоrk in the file submission to receive pаrtiаl credit. A small plant produces 3 different products, A B C, and they use a Kanban pull system. The demand for the A is 1050 units per day, for B is 500 units per day, and for C is 275 units per day. A is produced and transported in containers that can hold up to 3 units, B is transported in pairs, and C is transported individually. There are 2 units of setup time when switching between the three products. Assuming that the replenishment lead time is 3 days for each product, determine the number of kanbans needed for each product. (10pts) [ProductAKanbans] [ProductBKanbans] [ProductCKanbans]