Q9) Pleаse shоw yоur wоrk in the file submission to receive pаrtiаl credit. An MRP system is used to plan production for a finished product. The planned lead time for the product is 2 weeks. The system uses Lot-for-Lot production. Determine the Planned Order Releases for weeks 1 – 6. Please fill in the Scheduled Receipts, the Net Requirements, and the Planned Order Releases below. Week 0 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Gross Requirements 2222 3333 4444 5555 6666 7777 Scheduled Receipts/On-hand 14034 Net Requirements Planned Order Releases On-Hand Week 1 = [OnHandW1]; On-Hand Week 2 = [OnHandW2]; On-Hand Week 3 = [OnHandW3]; On-Hand Week 4 = [OnHandW4]; On-Hand Week 5 = [OnHandW5]; On-Hand Week 6 = [OnHandW6]; Net Req. Week 1 = [NetW1]; Net Req. Week 2 = [NetW2]; Net Req. Week 3 = [NetW3]; Net Req. Week 4 = [NetW4]; Net Req. Week 5 = [NetW5]; Net Req. Week 6 = [NetW6]; POR Week 0 = [PORW0]; POR Week 1 = [PORW1]; POR Week 2 = [PORW2]; POR Week 3 = [PORW3]; POR Week 4 = [PORW4]; POR Week 5 = [PORW5]; POR Week 6 = [PORW6];