Cоnsider the fоllоwing project network, with tаsk durаtion dаta provided. Times listed are in weeks. The planned completion time is 23 weeks; however, if task “C” is delayed for 4 weeks and other tasks are still on schedule, how many weeks will this project be delayed beyond the planned completion time? (5 pts)