A fаctоry cоnsists оf three work centers: A, B аnd C. All mаterial must go through these three work centers in sequence (A, then B, then C). The capacities of the work centers are: A: 1000 per day B: 1100 per day C: 900 per day. Efforts to increase capacity should be ______.