Argоn, а prоject mаnаger, frantically wоrks on academic projects to raise funds for his real passion, muskox ranching (their fur is very valuable!). He has identified eight tasks and developed three separate time estimates (all in days) for the next big project on the farm, replacing the fence at the emu enclosure. Tasks, precedence requirements, and time estimates are shown in the table. Determine the following: Duration for each task (PERT) Total project duration Which tasks have slack Critical Path Activity A time best B time usual C time worst Predecessor Corner Posts 4 10 15 -- String Line 10 14 16 -- Dig Holes 8 14 18 Corner Posts Plant Posts 14 20 22 String Line Weld Top Bar 9 13 16 String Line Paint 15 20 25 Dig Holes, Plant Posts Tack Wire 6 12 18 Weld Top Bar Add Gate 2 5 9 Paint, Tack Wire