A project consists of eleven activities (all times are given…
A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table. Assume that all four workers employed by this organization are generalists and are able to work on any of the tasks. What day does activity H start under a leveled project with the four worker limitation?ActivityActivity timeWorkers NeededPredecessorA101B42C73AD41AE82BF93C,EG131DH142E,GJ133FK101H, JL52K