The imаge is аn AON prоject netwоrk diаgram. The same netwоrk information is provided in the table that follows. AON Project Network: Activities, Predecessors, and Duration Activity Predecessor Duration A n/a 10 B A 5 H A 4 C B, H 4 D B 4 G H 8 E C, D 4 F E, G 5 The paths through the network are:A-H-G-FA-H-C-E-FA-B-C-E-FA-B-D-E-F Use the AON information provided above to answer the following question:How long would it take to complete this project?